Concept → Registration → Feasibility → Appraisal → Approval → Budgeting → Procurement → Implementation → Monitoring → Evaluation → Closure. AI can appraise, never approve or release funds.
PB-0001Energy and hydropowerHigh risk
Upper Arun Hydroelectric Project
Sankhuwasabha, Koshi · Owner: NEA · 25,00,000 beneficiaries
Stage: Implementation · Physical progress 14% · Spent Rs 21.0 Arba / Rs 140.0 Arba
PB-0002Roads and infrastructureMedium risk
Mid-Hill Highway Section 4
Gandaki Province · Owner: Department of Roads · 9,00,000 beneficiaries
Stage: Monitoring · Physical progress 68% · Spent Rs 12.6 Arba / Rs 18.0 Arba
PB-0003Digital technology and AIMedium risk
Smart Ward Digital Service Centres
All 6,743 wards · Owner: MoCIT · 3,00,00,000 beneficiaries
Stage: Budgeting · Physical progress 5% · Spent Rs 30.0 Crore / Rs 4.8 Arba
PB-0004Agriculture and food securityLow risk
Sunkoshi–Marin Irrigation Diversion
Madhesh & Bagmati · Owner: MoEWRI · 11,00,000 beneficiaries
Stage: Monitoring · Physical progress 72% · Spent Rs 30.0 Arba / Rs 46.0 Arba
PB-0005Education and skillsLow risk
Provincial Technical Universities
7 provinces · Owner: MoEST · 70,000 beneficiaries
Stage: Appraisal · Physical progress 0% · Spent Rs 0 / Rs 9.0 Arba